Planned and actual hours are captured per project, per task and per resources in BarnOwl.
When you create the project, navigate to the Resources tab and expand the project tasks. The selected resources will be visible under the units in the audit. Enter the planned hours for each resource next to their names. The link below shows more details on this step –
Click here.
Planned hours can also be updated after the project has been created in the Project Detail button > Resource Allocation tab or from the Resource Allocation Register. For detailed steps on how to do that, click on the following link
Click here.
Actual hours are captured within the project from the Capture menu > Actual Hours. The link below gives more details on how to do this
Click here.